A stacker in use at the Wiggins Island Coal Export Terminal.
A stacker in use at the Wiggins Island Coal Export Terminal. Mara Pattison-Sowden

Wiggins Island payment fight continues

CIVIL Mining and Construction and Wiggins Island Coal Export Terminal returned to court for a hearing on Monday.

The parties are arguing over payments related to delays and disruptions of works at the Gladstone terminal.

In June, Brisbane Supreme Court Justice Peter Flanagan ordered WICET to pay CMC $4.086 million for the disruptions.

The Gladstone Observer reported in June that the biggest of CMC's four claims related to variations and directions that affected the bulk earthworks of Reclamation C Bunds for which they were seeking $5.8 million.

Justice Flanagan on Monday heard from the parties on other matters relating to the case.

- NewsRegional


Students learn life lessons through dance

Students learn life lessons through dance

Gatton school collects two awards at Wakakirri.

Tractors tackle 153km trek

Tractors tackle 153km trek

More than 60 drivers and their passengers took part.

Sick and tired after dust issues ramp up

Sick and tired after dust issues ramp up

He believes traffic in the area has cause the issues to ramp up.

Local Partners